NEW QUESTION 37
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
According to Maslow’s hierarchy of needs, giving the employees an award that acknowledges their achievements is most likely to satisfy which level of need?

 
 
 
 

NEW QUESTION 38
Meetings require:

 
 
 
 

NEW QUESTION 39
An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.
Answer the question using a straight line depreciation and a 10% interest rate.
If $100,000 is needed to purchase a piece of equipment 3 years from now, how much money needs to be invested today assuming a 10% rate of return (rounded to the nearest thousand)?

 
 
 
 

NEW QUESTION 40

The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
At the end of Year 4, the commodity which experienced the greatest projected percentage price index increase over today is:

 
 
 
 

NEW QUESTION 41
NO: 37

The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
The entire pipe has been received, hangers have been installed, and all pipes are in place. None has been welded or flushed. What percent complete is this project?

 
 
 
 

NEW QUESTION 42
An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.
Answer the question using a straight line depreciation and a 10% interest rate.
Which of the following should be included in the life-cycle cost analysis of a power plant?

 
 
 
 

NEW QUESTION 43
The purpose of a communication must be understood by ____________ if the message is to be clear to the

 
 
 
 

NEW QUESTION 44
____________is defined as the earned work hours or dollars for all accounts divided by the budgeted work hours or dollars for all accounts.

 
 
 
 

NEW QUESTION 45
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
Resource planning must take all of the following into account except:

 
 
 
 

NEW QUESTION 46

The following question requires your selection of CCC/CCE Scenario 28 (3.7.50.1.7) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
In the A relationship, the subcontractor might use an unbalance bid to:

 
 
 
 

NEW QUESTION 47
Listening to what is being said by all members of a group or audience and then summarizing or interpreting is called______________.

 
 
 
 

NEW QUESTION 48
A concrete slab measuring 10 feet wide by 13.5 feet long by 6 inches deep is to be installed. How many cubic yards of concrete will be required?

 
 
 
 

NEW QUESTION 49

The following question requires your selection of CCC/CCE Scenario 28 (3.7.50.1.7) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
If the owner in B has as his primary goal to get the project completed and on line as fast as possible, then he would most likely use the ______________type of contract.

 
 
 
 

NEW QUESTION 50
____________ is the application of total resources ($-workers-supports) and activity durations of the logic diagram.

 
 
 
 

NEW QUESTION 51

The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
10,278 hours have been expended to date. The CPI at this point in time is 0.93. SPI is
1.03. How many hours were planned?

 
 
 
 

NEW QUESTION 52

The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
6,573 hours have been expended to date. Planned completion at this time is 60%. The project is determined to be 55% complete. How many hours have been earned?

 
 
 
 

NEW QUESTION 53

The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen., using the drop down menu, to reference during your response/choice of responses.
Calculate the weighted average unit cost.

 
 
 
 

AACE International CCP Dumps Cover Real Exam Questions: https://www.prepawaytest.com/AACE-International/CCP-practice-exam-dumps.html