2025 Best PMI-RMP Exam Preparation Material with New Dumps Questions [Q37-Q58]

Rate this post

2025 Best PMI-RMP Exam Preparation Material with New Dumps Questions

Free PMI-RMP Exam Files Verified & Correct Answers Downloaded Instantly

The Project Management Institute (PMI) Risk Management Professional (PMI-RMP) certification is a globally recognized and highly respected designation for professionals in the field of risk management. The PMI-RMP certification is designed for individuals who want to demonstrate their expertise in identifying, assessing, and mitigating project risks. PMI Risk Management Professional certification is ideal for project managers, risk managers, and other professionals who are responsible for managing risk in their organizations.

 

NEW QUESTION 37
A risk manager creates a survey for project stakeholders to obtain their opinions on high levels of risk. Key questions in the survey address acceptable levels of cost increases and schedule delays.
What is the risk manager trying to determine?

 
 
 
 

NEW QUESTION 38
A project team identifies that there is a probability of missing a key milestone in a project. The team wants to move forward with the risk response planning.
What should the risk manager complete first?

 
 
 
 

NEW QUESTION 39
You are interviewing members of a project team to test their understanding of the assigned risk responses as risk owners. You and the project manager are working together to evaluate the risk responses to determine their effectiveness in the project. What project management technique are you performing with the project manager in this scenario?

 
 
 
 

NEW QUESTION 40
When processing freight invoices for a project, the project manager notices the shipping costs exceeded the budget due to increased fuel costs. The risk manager included this risk in the project’s contingency allowance. When reviewing the project budget execution reports, the project manager notices unused budget remaining in other closed tasks of the project that could cover the additional shipping costs.
What should the project manager do?

 
 
 
 

NEW QUESTION 41
Melody is the project manager for her organization. She has created a risk response to conduct more tests on the software her project is creating. The identified risk that prompted this response was that the software is mission-critical and must be flawless before it can be put into product.
What type of a risk response has Melody used in this scenario?

 
 
 
 

NEW QUESTION 42
A project is at the final development stage. The test lead informs the risk manager that a key feature may not be testable due to changes in the environment What should the risk manager do?

 
 
 
 

NEW QUESTION 43
Linda is the project manager of the NAB Project. One of the risks her project team has identified is too dangerous for the project team to manage internally so she has hired a vendor to complete this portion of the project and to manage the identified risk. What risk response has Linda used in this instance?

 
 
 
 

NEW QUESTION 44
The project team has correctly identified, assessed, and planned responses for a project’s risks. The risk manager is required to prepare a quarterly report on the performance of managing the risks.
What are two options the risk manager should consult for the analysis? (Choose two.)

 
 
 
 
 

NEW QUESTION 45
Don has hired Jerry, a contractor, to complete a portion of his project work. The contract used was a cost-plus contract. If Don were to perform a risk audit, who would carry the risk in this scenario?

 
 
 
 

NEW QUESTION 46
You are the project manager of the GGK project for your company. The GGK project has a budget of
$1,265,100 and is currently 40 percent complete. In this project, you elected to add labor to the project to increase the likelihood of completing the project early as the project was only scheduled to be 35 percent complete at this time. This positive risk response, while keeping the project ahead of schedule, has added significant costs to the project. You have already spent $575,000 to reach this point in the project. Management would like to know what your cost performance index and the schedule performance index is for this project.
What are these values?

 
 
 
 

NEW QUESTION 47
In addition to monitoring and controlling the project risks for their status and information the risk monitoring and controlling process accomplishes four key things for a project. Which one of the following is NOT a determination that is made by the risk monitoring and controlling process?

 
 
 
 

NEW QUESTION 48
A project manager is working on a high priority and high profile project. The project team had identified three opportunities, and after analysis, risk responses were recorded. Although risk responses were adequate for the identified opportunities, two of those opportunities were not acted upon. During the risk audit, the project manager found out that several of the planned risk responses were not implemented.
What should the project manager have done to avoid this?

 
 
 
 

NEW QUESTION 49
What is an example of legal and regulatory requirements and/or constraints when assessing a project environment for threats and opportunities?

 
 
 
 

NEW QUESTION 50
Mary is the project manager of PKT project. In Mary’s project there are certain enterprise environmental factors that require Mary to use modeling and simulation techniques to predict the likelihood of achieving cost and schedule objectives in the project. Mary is using a technique for which the cost estimates are chosen at random for each iteration of the analysis, such as pessimistic, most likely, and worst-case scenarios. What type of analysis is Mary using in this project?

 
 
 
 

NEW QUESTION 51
You are the project manager of the HJK Project for your organization. You and the project team have created risk responses for many of the risk events in the project. Where should you document the proposed responses and the current status of all identified risks?

 
 
 
 

NEW QUESTION 52
Which of the following should multicultural groups be aware of on a project relative to risk?

 
 
 
 

NEW QUESTION 53
A home solar panel project has many internal and external stakeholders including households, businesses, community groups, electric utility companies, local government officials, landlords, and investors. What should the project manager do when engaging stakeholders?

 
 
 
 

NEW QUESTION 54
You are the project manager of the HJK Project for your organization. You and the project team have created risk responses for many of the risk events in the project. Where should you document the proposed responses and the current status of all identified risks?

 
 
 
 

NEW QUESTION 55
Your project has several risks that may cause serious financial impact should they happen. You have studied the risk events and made some potential risk responses for the risk events but management wants you to do more. They’d like for you to create some type of a chart that identified the risk probability and impact with a financial amount for each risk event. What is the likely outcome of creating this type of chart?

 
 
 
 

NEW QUESTION 56
A risk manager administered a pre-workshop risk survey in preparation for the upcoming workshop. The workshop invitees participated in the survey and submitted many risks encompassing all project phases and risk areas. The risk manager sorts risks by similarities and categories for the workshop.
What should the risk manager do next to visually organize the risks?

 
 
 
 

NEW QUESTION 57
A newly assigned risk manager realizes that a project has unrealistic funding and low resources. Which document should the risk manager review?

 
 
 
 

NEW QUESTION 58
A project manager is creating a risk management plan. The project sponsor does not see the need for additional risk management, believing that the only risks to the project are financial risks.
What procedure could the project manager use to identify other potential topics such as technical, quality, performance, project, management, internal and external risks?

 
 
 
 

To be eligible for the PMI-RMP certification exam, candidates must have a secondary degree (high school diploma, associate’s degree, or global equivalent) and at least 4,500 hours of project risk management experience. Alternatively, candidates can also have a four-year degree (bachelor’s degree or global equivalent) and at least 3,000 hours of project risk management experience. PMI-RMP exam consists of 170 multiple-choice questions that must be completed within 3.5 hours. The questions are based on the PMI-RMP Exam Content Outline, which covers five domains of risk management.

 

Instant Download PMI-RMP Dumps Q&As Provide PDF&Test Engine: https://www.prepawaytest.com/PMI/PMI-RMP-practice-exam-dumps.html

Leave a Reply

Your email address will not be published. Required fields are marked *

Enter the text from the image below