Q47. Determine the correct formula and date for the late finish for Activity 9004.

 
 
 
 

Q48. Determine the correct formula and date for the late start for the Activity 11001:

 
 
 
 

Q49. If Activity E’s duration changes to 4 months, what is the overall duration of the project.

 
 
 
 

Q50. Which of the following will NOT affect the total float calculation of a non-resource leveled schedule?

 
 
 
 

Q51. Which is NOT an industry-recognized methodology for quantifying critical delay?

 
 
 
 

Q52. Which of the following are NOT considerations or constraints of the planning process for construction scheduling?

 
 
 
 

Q53. Crane operators require 1 hour prep and 1 hour clean-up and inspection per day. There is only 1 crane operator allocated per crane. Crane operators are not allowed to work more than 8 hours a day. Lunchtime break lasts 1 hour. Assuming a 10 minute cycle time, how many lifts per day can be expected?

 
 
 
 

Q54. What is the cycle time?

 
 
 
 

Q55. Midway through the project you received an executed change order for this project, adding thirty-three days to the contract for weather delays. In its simplest form, how would your next project update display the changed condition?

 
 
 

Q56. For the late finish for Activity 11001, select the most appropriate response for transitioning from the forward pass.

 
 
 
 

Q57. In the “normal” schedule, excluding Activity 1000, what activity(s) are concurrent with Activity 3001?

 
 
 
 

Q58. Of the following update procedures, which is the least important in achieving an accurate forecast for completion of a construction schedule?

 
 
 
 

Q59. What does the heavy, vertical line at “X” represent?

 
 
 
 

Q60. Time-scaled logic diagrams are

 
 
 
 

Q61. What is the relationship depicted between Activity G and Activity H?

 
 
 
 

Difficulty in Writing Planning & Scheduling Professional (PSP) Exam

All exams can turn out to be very difficult if not well prepared. The main preparation material for the Planning & Scheduling Professional (PSP) Exam is the industry experience and related college degree as this is the prerequisite of the exam and is a must for an applicant as stated by AACE. Refer to the “How to study” section above to use the official resources to best prepare for the exam. One of the key problems faced by most candidates is to choose the right research materials for their exam preparation since they use the internet to find too much data that makes it difficult for them to trust, which would be helpful for them. PSP exam dumps pdf are designed in such a way to make better preparatory material. This exam can turn out to be a very difficult certification if not well prepared. We always recommend studying the PSP practice exam dumps before actually appearing for the exam. Applicants may, however, clear the exam with the right concentration and the right preparation material.

PrepAwayTest have the most up-to-date PSP exam dumps, having a fair understanding of the question trend being asked in real certification with the help of these exam dumps.

 

Read Online AACE-PSP Test Practice Test Questions Exam Dumps: https://www.prepawaytest.com/AACE-International/AACE-PSP-practice-exam-dumps.html

Leave a Reply

Your email address will not be published. Required fields are marked *

Enter the text from the image below