NEW QUESTION 21
Regarding the FIDIC Silver Book (both editions), if a part of the Works is to be paid according to quantity supplied or work done, appropriate provisions must be included in the Particular Conditions. Is this statement true or false?

 
 

NEW QUESTION 22
Under the FIDIC Red Book (edition 2017), the Engineer has suspended works to come to a change of the design of a part of the Works. After expiry of 84 days of suspension, the Contractor gave notice thereof.
Following this notice, the suspension was not lifted within 28 days. What two statements are correct in such a situation?

 
 
 
 

NEW QUESTION 23
You are the Contract Manager of the Engineer and person Y is the Contract Manager of the Employer in a construction project under FIDIC 2017 Red Book. The project is late in schedule and Y has issued Employer’s claim on Delay Damages. You have asked Y to consider whether the Contractor’s delay to completion is a reflection of cash-flow shortfall from interim payments before making deductions to the Contractor’s payment. Y replied that even if the Contractor pays Delay Damages to the Employer, the Contractor is still obliged to complete the Works and is not relieved from its duties and obligations. You warned Y of the risks of further reduction of cash-flow by the deduction of Delay Damages from payments. As this could worsen the situation of the Contractor, leading to further delays to the completion of the Works. Who is right?

 
 
 
 

NEW QUESTION 24
Choose which one statement consists of an example of an unclear and ambiguously drafted Particular Conditions.

 
 
 
 

NEW QUESTION 25
You are the Contract Manager in a highway project using FIDIC Red Book (edition 1999). You work for the Employer- a highway management agency. During the tender period, you are informed of a specific Commencement Date required by the directors of the agency. Which two of the following approaches to inform the tenderers of this date are clearly and unambiguously drafted?
Choose all of the correct answers (multiple possibilities).

 
 
 
 

NEW QUESTION 26
Under the FIDIC Red, Yellow, and Silver Books (both editions), the Employer has an obligation to give a detailed notice to the Contractor about intended changes that are material to its financial arrangements.

 
 

NEW QUESTION 27
The Contractor is entitled to an advance payment. Applying FIDIC Red Book (edition 1999), which two of the following statements are correct?
Choose all of the correct answers (multiple possibilities):

 
 
 
 

NEW QUESTION 28
You are the Contract Manager of the Employer’s Representative in a Thermal Power Plant Project. The Contract for this project is EPC Turnkey Contract using the FIDIC Silver Book (edition 2017) with a Contract Price of 28 million USD. The Employer’s Requirements require that: “the Contractor design in accordance with international and national technical regulations, and standards, [etc.]”.
For piling works, the Employer’s Requirements state that the Contractor will design according to a specific national standard for piling works NTS-PW-01. After all piles for the jetty have been installed, a pile load test on lateral bearing capacity shows that actual lateral bearing capacity is much lower than the calculated lateral bearing capacity. It was later revealed by the Technical Standard Committee that there was a typo mistake during preparation of the NTS-PW-01 (translated from a foreign standard). The lateral bearing capacity of installed piles had been substantially overestimated as a result of this typo. Contractor submits a claim for
200,000 USD regarding extra costs for installing additional piles as a result of errors in the Employer’s Requirements.
In the hydrological information of Site Data provided by the Employer, the annual high water level is 4.0m.
However, during the design stage, with updated data from local stations along the rivers, the Contractor found out there was a mistake in the calculation. The annual high water level should be 4.5m. As a result, the Contractor has to design and build additional flood walls along the river to protect the Plant from flooding.
The Contractor claims an amount of 300,000 USD to construct the flood wall, based on Unforeseeable difficulties.
As the Employer’s Representative, after you have consulted with both Parties but failed to reach agreement, you will make a fair determination of the Claims of the Contractor.
In your “Notice of the Employer’s Representative’s determination”, what is your determination for the Contractor?

 
 
 
 

NEW QUESTION 29
Which two of the following statements are correct, regarding the Programme under FIDIC Red, Yellow and Silver Books (edition 2017)?
Choose all of the correct answers (multiple possibilities).

 
 
 
 

NEW QUESTION 30
Which two statements reflect an INCORRECT application of a Golden Principle?

 
 
 
 

NEW QUESTION 31
Which FIDIC Book (edition 2017) should be considered first by an Employer that is an experienced employer who knows exactly what they want from a design & engineering perspective?

 
 
 
 

NEW QUESTION 32
There are four reasons that the Employer/Contractor shall advise in advance each other and the Engineer of any known or future events or circumstances.
Which two of the following statements areNOTapplicable reasons?
(Choose all correct answers – multiple possibilities)

 
 
 
 

NEW QUESTION 33
Under the FIDIC Red Book (edition 1999): the Contractor submitted Final Statement in accordance with the Contract and the Contractor wants to correct it. Can the Contractor correct the Final Statement?

 
 

NEW QUESTION 34
The Employer has prepared a contract for a waste-to-energy project based on the FIDIC Yellow Book (edition
1999). You are preparing negotiations on behalf of one of the Subcontractors with the Contractor. The main Contractor will manage the design and build of the Works, whereby the Subcontractor will deliver critical systems regarding power generation and cooling. The Contractor intends to contract the main Contract back- to-back with the Subcontractor. In the proposed back-to-back subcontract, the following amendment is proposed through Particular Conditions:
“Sub-Clause 4.4. The following paragraph is added: The Subcontractor is required to scrutinize the Employer’s Requirements in a manner identical to the obligations of the Contractor as stated in Sub-Clause
5.1 of the Main Contract. The Subcontractor will indemnify and hold harmless (up to the maximum liability of the Subcontractor) the Contractor with regard to any error, fault or other defect found in the Employer’s Requirements, its items of reference or Contractor’s design of the Works for the scope part for which Subcontractor is contracted.” What is your advice to the Subcontractor (SC) in regard to entering this proposed subcontract?

 
 
 
 

NEW QUESTION 35
Which one of the following documents constitutes a contract and is considered binding on both parties, when the Employer wants to award the Contract to the tenderer?

 
 
 
 

NEW QUESTION 36
Which of the following statements are not correct?
Choose all of the correct answers (multiple possibilities).

 
 
 
 
 

NEW QUESTION 37
What does discharge confirm under the FIDIC Red Book (edition 1999)?

 
 
 
 

CCM Sample Practice Exam Questions 2026 Updated Verified: https://www.prepawaytest.com/Medical-Professional/CCM-practice-exam-dumps.html

Related Links: myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt

Leave a Reply

Your email address will not be published. Required fields are marked *

Enter the text from the image below